Concrete Mixing Plant How to Rurn On and Off
The concrete mixing plant on the power station and the power off is a necessary process, the reasonable and safe switch concrete mixing station not only can reduce the accident, but also can ensure the service life of the concrete mixing station. So the station master to plan to improve the operation of the safety switch station of the work flow to ensure the smooth production of the. Today small haomei machines for everyone to do a brief analysis, so we used correctly.
Concrete mixing station starting sequence
The control switch of the motor cabinet is opened, including the main engine, the cement silo, the pump, the mixing chamber, the flat belt, the inclined belt, and the discharge switch. Then open the computer host. After opening the first test of the mechanical movement capacity, the first operation of the diagonal belt, and then run the host, and finally to run flat belt. It can guarantee the inside of the scrap can work out. Maintain mechanical integrity. If the normal operation of the case, you can open the pump, batching machine, and so on the machine began to work properly. If some of the equipment is not up to the right, it is said that there is no normal start, long time will cause damage to the device, this situation is to resolutely put an end to.
concrete mixer plant equipment shutdown sequence
Ingredients (including aggregate, cement) off for water, feeding off (belt without stock) mixing console off (concrete mixer tank no deposit material) discharging belt off (belt no deposit material) storage bin door air pressure organs cleaning stirring tank shut off the water valve switch off the total power.
Above is the small concrete batching plant to the correct switch machine steps, no rules, no Cheng Fangyuan, so the user in the mixing station to take seriously.